1. Gantt charts
A Gantt chart is a horizontal bar chart of the project schedule. Each task has a bar along a timeline, and the length of the bar is the task's duration. Arrows between bars show the dependencies between tasks, and the critical path can be marked.
To create one, take each task's duration and predecessors from the task list. A bar starts only when its predecessors have finished. Tasks with no dependency between them are drawn concurrent.
To interpret one, read what can be seen: the bars, their positions and the arrows. A percentage bar inside a task bar, or a different colour for overdue tasks, shows progress.
Examiner insight
Worked example 14 marks
A Gantt chart is required to show the project schedule for the creation of a new database.
The project tasks required to create the Gantt chart are in the table.
Complete the Gantt chart for this project. Clearly show the longest path through the project on your chart.
| task number | name of task | duration of task (weeks) | predecessor task(s) |
|---|---|---|---|
| 1 | designing the database | 1 | |
| 2 | creating tables, relationships and queries | 2 | 1 |
| 3 | inputting test data and testing | 2 | 2 |
| 4 | evaluating the database | 2 | 3 |
| 5 | writing documentation for the database | 4 | 1 |
| 6 | deploy the database for use | 1 | 4, 5 |
- 1
All task lengths correct: task 1 is week 1, task 2 weeks 2–3, task 3 weeks 4–5, task 4 weeks 6–7, task 5 weeks 2–5, task 6 week 8. [1]
- 2
Task 5 is drawn concurrent with tasks 2 and 3, starting after task 1. [1]
- 3
All dependencies correct: task 6 starts only when both task 4 and task 5 have finished. [1]
- 4
Longest path marked: tasks 1, 2, 3, 4, 6, which is 1 + 2 + 2 + 2 + 1 = 8 weeks. [1]