Tools and techniques for project management tasks

Information Technology 9626 Chapter Notes

Last updated November 2026

ShareWhatsAppPost

Tools and techniques for project management tasks notes as a printable PDF.

Read online free. Download a watermarked copy with a free account.

Read the notes

The full Tools and techniques for project management tasks notes as text: skim, search, and jump between subtopics.

~18 min read

1. Gantt charts

A Gantt chart is a horizontal bar chart of the project schedule. Each task has a bar along a timeline, and the length of the bar is the task's duration. Arrows between bars show the dependencies between tasks, and the critical path can be marked.

To create one, take each task's duration and predecessors from the task list. A bar starts only when its predecessors have finished. Tasks with no dependency between them are drawn concurrent.

To interpret one, read what can be seen: the bars, their positions and the arrows. A percentage bar inside a task bar, or a different colour for overdue tasks, shows progress.

Examiner insight

“Weaker candidates did not accurately transfer the data given in the table onto their Gantt chart or correctly put the tasks into an appropriate order.” “Strong answers to this question referred to the timeline, the bars showing the durations of tasks, and the arrows showing the dependencies and critical path.”

Worked example 14 marks

A Gantt chart is required to show the project schedule for the creation of a new database.

The project tasks required to create the Gantt chart are in the table.

Complete the Gantt chart for this project. Clearly show the longest path through the project on your chart.

task numbername of taskduration of task (weeks)predecessor task(s)
1designing the database1
2creating tables, relationships and queries21
3inputting test data and testing22
4evaluating the database23
5writing documentation for the database41
6deploy the database for use14, 5
  1. 1

    All task lengths correct: task 1 is week 1, task 2 weeks 2–3, task 3 weeks 4–5, task 4 weeks 6–7, task 5 weeks 2–5, task 6 week 8. [1]

  2. 2

    Task 5 is drawn concurrent with tasks 2 and 3, starting after task 1. [1]

  3. 3

    All dependencies correct: task 6 starts only when both task 4 and task 5 have finished. [1]

  4. 4

    Longest path marked: tasks 1, 2, 3, 4, 6, which is 1 + 2 + 2 + 2 + 1 = 8 weeks. [1]

2. PERT charts: components and dependencies

A PERT chart (Performance Evaluation and Review Technique) shows the tasks in a project and how they depend on each other. The work breakdown structure (WBS) technique divides the project into smaller activities, which can be assigned to individual workers or teams. The chart needs each task's duration and its dependencies (predecessors), and it shows the start and end points.

Float is the amount of time a task can be delayed before it affects the start of the next task. A milestone is a point in the project when tasks or criteria are met. A milestone is not a goal. A deliverable is an output in a logical or tangible form from a task or project, such as a product agreed by the stakeholders.

A dependency describes the reliance of one task upon another. In one type, a task cannot start until other tasks have finished. Others are Finish-to-Finish, Start-to-Start and Start-to-Finish. Dependencies show managers the order in which tasks are carried out, and they enable the allocation of resources.

Examiner insight

“Descriptions of how float is calculated did not answer the question. A key point about float is that it is the amount of time that a task can overrun before affecting the succeeding task(s).” “The most common mistake was to repeat or reword the dependency stated in the question.”

Worked example 16 marks

Performance Evaluation and Review Technique (PERT) charts are used when planning a project.

(a) Describe each of these components of a PERT chart:(i) float,(ii) milestone.

(b) In a project, tasks are linked to each other by dependencies.(i) One type of dependency is when a task cannot start until other tasks are fully completed and finished. Describe two other types of dependency that can be found in a project.(ii) Describe two uses of dependencies in PERT charts.

  1. 1

    (a)(i) Float: the amount of time a task can be delayed before affecting the start of the next, dependent task. [1]

  2. 2

    (a)(ii) Milestone: a point in the project when tasks or criteria are met. [1]

  3. 3

    (b)(i) Finish-to-Finish: a task cannot end until another task also ends. [1]

  4. 4

    (b)(i) Start-to-Start: a task cannot start until another task starts. [1]

  5. 5

    (b)(ii) Shows managers the order in which tasks should be carried out. [1]

  6. 6

    (b)(ii) Enables the allocation of resources. [1]

3. Activity-on-node and activity-on-arrow charts

A PERT chart is drawn in one of two ways. Before either can be drawn, the task list needs each task's duration and its dependencies.

In an activity-on-node chart the tasks sit at the nodes, in boxes containing the timings. In an activity-on-arrow chart the milestones sit at the nodes, in circles, and the tasks sit on the arrows.

Activity-on-arrow may have dummy dependencies for complex tasks, and a lot of data written on the arrows makes it cluttered and harder to interpret. Activity-on-node is easier to read and to amend.

Examiner insight

“Good answers included a suitable diagram that showed how each of the tasks linked together but many did not include a start and finish point and often arrows to show the direction through the diagram were missing.” “Common errors were those of omission e.g. not showing all of the timings.”

Worked example 16 marks

PERT charts can be drawn either as activity-on-node diagrams or as activity-on-arrow diagrams.

Compare, by commenting on the similarities and differences, activity-on-node and activity-on-arrow PERT diagrams.

  1. 1

    Similarity: both are graphical representations that show the tasks needed to complete a project. [1]

  2. 2

    Similarity: both show the critical path through a project. [1]

  3. 3

    Difference: activity-on-node shows tasks at the node, in boxes containing timings. [1]

  4. 4

    Difference: activity-on-arrow shows milestones at the nodes, in circles, with tasks on the arrows. [1]

  5. 5

    Comparison: activity-on-node is less cluttered, so easier to read and interpret. [1]

  6. 6

    Comparison: calculating the critical path is easier with activity-on-node. [1]

4. The critical path and CPM

The critical path is the longest path through the project. It gives the shortest possible time for completion of the project, and it is the longest sequence of tasks that must be done on time. Tasks on it have no float.

The Critical Path Method (CPM) finds it in steps: list the tasks, identify the dependencies, estimate the duration of each task, draw the network diagram, work out the longest route, then calculate the total float.

Critical path analysis is used for work flow control, for example authorising work, costings and allocating resources.

Examiner insight

“Poor answers described what a critical path is but gave no further information.” “Strong responses included the visual representation of the whole project, the shortest possible time that a project would take and any possible alternative paths through a project.”

Worked example 16 marks

A project manager is trying to find the critical path through a project.

(a) Describe what is meant by the critical path.

(b) The first step in finding the critical path through a project is to list the tasks necessary to complete the project. Describe four other steps that a project manager could take to find the critical path.

  1. 1

    (a) The longest path (from task to task) through the project. [1]

  2. 2

    (a) The shortest possible time for completion of the project. [1]

  3. 3

    (b) Identify the dependencies between tasks. [1]

  4. 4

    (b) Estimate the duration of each task. [1]

  5. 5

    (b) Work out the longest sequence of tasks needed to finish the project. [1]

  6. 6

    (b) Calculate the shortest possible time in which the project can be finished. [1]

5. Calculating the critical path and float

List every path from start to finish. Add the durations along each path. The largest total is the longest path, which is the critical path, and its length is the shortest possible time for the project.

Show every path. A bare total of days does not show where the value came from.

A task on the critical path has zero float. A task on a shorter path can be delayed by the difference before it affects the whole project, so its total float is the critical path length minus the longest path through that task.

path length = sum of the durations of its tasks

float of a task = critical path length - longest path through the task

Examiner insight

“Good answers showed that tasks 2, 3, 4 and 5 should have a zero float because they are on the critical path which would take 16 days, while the path via tasks 1, 3 and 4 would take 12 days so task 1 could have a float of 4 days before it affects the overall time for the project.” “A good answer gave the path and its length.”

Worked example 14 marks

A project has five tasks. Task A takes 2 days and has no predecessor. Task B takes 3 days and follows A. Task C takes 4 days and follows A. Task D takes 2 days and follows B. Task E takes 3 days and follows C and D.

(a) Find the critical path and the shortest possible time for the project.

(b) Find the float of task C.

  1. 1

    The paths are A, B, D, E and A, C, E. [1]

  2. 2

    A, B, D, E = 2 + 3 + 2 + 3 = 10 days and A, C, E = 2 + 4 + 3 = 9 days. [1]

  3. 3

    The longest path is the critical path: A, B, D, E. The shortest possible time is 10 days. [1]

  4. 4

    Float of C = 10 - 9 = 1 day. [1]

6. Advantages and disadvantages

Gantt charts give a visual overview of the schedule, show changes to the schedule clearly and can show milestones. Their drawbacks are that they need skill to create, are time-consuming to update, cannot show every detail of a complex project and cannot allow for contingency time.

CPM shows the critical and non-critical paths and calculates the project duration. It does not show the required resources, which a Gantt chart can. It relies on estimates of task durations, so the whole process can be invalid if the estimates are wrong. Activity-on-node PERT charts are easier to read and amend, while activity-on-arrow charts can be cluttered.

The tools work together. The dependencies on a PERT chart enable the construction of a Gantt chart, and they enable the calculation of the critical path.

In a discuss question, give both sides and explain each point.

Examiner insight

“Candidates who gave vague references to managing projects, to PERT and Gannt charts or to other aspects of project management were limited to low band marks.” “Typically, some of the stronger responses did detail the good and the bad aspects and explain them in detail to show meaning for example, ‘the reliance on estimates of the duration of task means that the whole process can be invalid if the estimates are wrong/inaccurate’.”

Worked example 15 marks

The Critical Path Method (CPM) and Gantt charts are used in project management.

Compare CPM with Gantt charts.

Your answer must include both similarities and differences.

  1. 1

    Similarity: both are visual or graphical representations of the project. [1]

  2. 2

    Similarity: both show the dependencies between tasks. [1]

  3. 3

    Difference: CPM is a network diagram with linked nodes, a Gantt chart is a horizontal bar chart. [1]

  4. 4

    Difference: CPM shows critical and non-critical paths. [1]

  5. 5

    Difference: a Gantt chart plots activities on a timescale, CPM does not. [1]

Recap

  • Gantt chart: horizontal bars on a timeline. Bar length is duration, arrows show dependencies.
  • Independent tasks are drawn concurrent. A task starts when all its predecessors finish.
  • PERT chart needs each task's duration and dependencies. Float is the amount of time a task can be delayed before affecting the next task.
  • Milestone: a point when tasks or criteria are met. Dependency types: Finish-to-Finish, Start-to-Start, Start-to-Finish.
  • Activity-on-node: tasks at the nodes. Activity-on-arrow: milestones at the nodes, tasks on the arrows.
  • Critical path: longest path, shortest possible project time, zero float. Show every path total.
  • Float = critical path length minus the longest path through the task.
  • Discuss advantages and disadvantages: give both, and explain each one.

End-of-chapter exercise

Test yourself on the whole chapter. Work through these before moving on.

  1. State what is meant by a milestone in a project.1 mark
    Answer
    1. A point in the project when tasks or criteria are met.

    Trap: A milestone is not a goal, which is an intended target to be achieved in a given time frame.

  2. A Gantt chart has bars and arrows. State what the length of a bar represents and what an arrow between two bars represents.2 marks
    Answer
    1. The length of a bar is the duration of the task.
    2. An arrow between two bars is a dependency between the tasks.

    Trap: Describing how a chart is derived or used when the question asks what can be seen on it.

  3. Give one benefit and one drawback to a project manager of using a Gantt chart.2 marks
    Answer
    1. Benefit: it gives a visual overview of the schedule.
    2. Drawback: it can be time-consuming to update, or it cannot show every detail of a complex project.

    Trap: Vague wording such as 'it is good for planning' names no feature of the chart, and examiners limited vague answers to low marks.

  4. State what is drawn at the nodes of an activity-on-node chart, at the nodes of an activity-on-arrow chart, and on the arrows of an activity-on-arrow chart.3 marks
    Answer
    1. Activity-on-node, nodes: the tasks, in boxes containing the timings.
    2. Activity-on-arrow, nodes: the milestones.
    3. Activity-on-arrow, arrows: the tasks.

    Trap: Swapping the two charts: tasks are at the nodes in activity-on-node, and milestones are at the nodes in activity-on-arrow.

  5. A project has four tasks. Task P takes 3 days and has no predecessor. Task Q takes 5 days and follows P. Task R takes 2 days and follows P. Task S takes 4 days and follows Q and R. (a) Calculate the length of each path through the project. (b) State the shortest possible time for the project.3 marks
    Answer
    1. (a)
    2. P, Q, S = 3 + 5 + 4 = 12 days and P, R, S = 3 + 2 + 4 = 9 days.
    3. (b)
    4. The longest path sets the shortest possible time: 12 days.

    Trap: Adding every duration (3 + 5 + 2 + 4 = 14) treats Q and R as one after the other. They can run at the same time.

  6. A Gantt chart numbers the days from 1, and each task starts on the first day it can. Task 1 takes 2 days and has no predecessor. Task 2 takes 3 days and follows 1. Task 3 takes 4 days and follows 1. Task 4 takes 2 days and follows 2 and 3. (a) State the first and last day of task 3. (b) State the day on which task 4 starts. (c) State how many days the project takes.4 marks
    Answer
    1. (a)
    2. Task 1 fills days 1 and 2, so task 3 starts on day 3 and, lasting 4 days, finishes on day 6.
    3. (b)
    4. Task 2 ends on day 5 but task 3 ends on day 6, so task 4 starts on day 7.
    5. (c)
    6. Task 4 fills days 7 and 8, so the project takes 8 days.

    Trap: Starting task 4 on day 6, straight after task 2, ignores that it also waits for task 3.

  7. A charity event has five tasks. A: book the hall, 2 days, no predecessor. B: print tickets, 3 days, follows A. C: sell tickets, 2 days, follows B. D: set up the stage and sound, 8 days, follows A. E: open the doors, 1 day, follows C and D. (a) Calculate the length of each path. (b) Name the critical path and state the shortest possible time for the event.4 marks
    Answer
    1. (a)
    2. A, B, C, E = 2 + 3 + 2 + 1 = 8 days and A, D, E = 2 + 8 + 1 = 11 days.
    3. (b)
    4. The longest path is the critical path: A, D, E.
    5. The shortest possible time is 11 days.

    Trap: Picking the path with the most tasks (A, B, C, E) instead of the path with the largest total.

  8. The critical path of a project takes 15 days. Task X is not on the critical path, and the longest path through task X takes 11 days. (a) Calculate the float of task X. (b) State the float of a task on the critical path. (c) Task X is delayed by 3 days. State whether the project finish time changes.4 marks
    Answer
    1. (a)
    2. Float = 15 - 11 = 4 days.
    3. (b)
    4. Zero.
    5. (c)
    6. No change: a delay of 3 days is within the float of 4 days.

    Trap: Subtracting the duration of task X instead of the longest path through it.

  9. A school play has six tasks and the days are numbered from 1. Each task starts on the first day it can. 1: write the script, 5 days, no predecessor. 2: audition actors, 3 days, follows 1. 3: make costumes, 6 days, follows 1. 4: build the set, 4 days, follows 1. 5: rehearse, 4 days, follows 2. 6: final performance, 1 day, follows 3, 4 and 5. (a) Calculate the length of each path and name the critical path. (b) State the float of task 3 and the last day on which task 3 can finish without delaying the performance.5 marks
    Answer
    1. (a)
    2. 1, 2, 5, 6 = 5 + 3 + 4 + 1 = 13 days; 1, 3, 6 = 5 + 6 + 1 = 12 days; 1, 4, 6 = 5 + 4 + 1 = 10 days.
    3. The critical path is 1, 2, 5, 6, which takes 13 days.
    4. (b)
    5. Float of task 3 = 13 - 12 = 1 day.
    6. Task 3 fills days 6 to 11, so it can finish as late as day 12.

    Trap: Stating that task 3 has no float because it holds the longest single task: only tasks on the critical path have zero float.

  10. A health centre is moving to a new booking system. The tasks are: 1: agree the requirements, 3 days, no predecessor. 2: install the server, 4 days, follows 1. 3: transfer the patient records, 7 days, follows 2. 4: train the reception staff, 5 days, follows 1. 5: write the user guides, 2 days, follows 1. 6: test the system with staff, 3 days, follows 3, 4 and 5. (a) Showing the length of every path, name the critical path and state the shortest possible time. (b) Calculate the float of task 4. (c) The trainer is ill, and training the reception staff takes 13 days instead of 5. Find the new critical path, the new shortest possible time and how many days later the project finishes.7 marks
    Answer
    1. (a)
    2. 1, 2, 3, 6 = 3 + 4 + 7 + 3 = 17 days; 1, 4, 6 = 3 + 5 + 3 = 11 days; 1, 5, 6 = 3 + 2 + 3 = 8 days.
    3. The critical path is 1, 2, 3, 6, so the shortest possible time is 17 days.
    4. (b)
    5. Float of task 4 = 17 - 11 = 6 days.
    6. (c)
    7. The delay is 13 - 5 = 8 days, more than the float of 6 days, so path 1, 4, 6 becomes 3 + 13 + 3 = 19 days.
    8. 19 days is longer than 17 days, so the new critical path is 1, 4, 6 and the shortest possible time is 19 days.
    9. The project finishes 19 - 17 = 2 days later.

    Trap: Giving only the new total with no paths shown, the bare value examiners reported, or keeping the old critical path when a delay is longer than the task's float.

Say this, not that

Wording that loses the mark, against the wording the mark scheme credits.

Loses the markGets the mark
A description of how float is calculated.Float is the amount of time a task can overrun before affecting the succeeding tasks.
A milestone is a goal for the project.A milestone is a point when tasks or criteria are met.
A task cannot start until the one before it finishes (the dependency the question already gave).Finish-to-Finish, Start-to-Start or Start-to-Finish dependency.
The critical path takes 16 days.The longest path is tasks 2, 3, 4 and 5 at 16 days, longer than the path via tasks 1, 3 and 4 at 12 days.

Frequently asked questions

How do you find the critical path in a project?
List every path from start to finish and add the durations along each path. The largest total is the longest path, which is the critical path, and its length is the shortest possible time for the project. Show every path, because a bare total of days does not show where the value came from.
How do you calculate the float of a task?
Float is the critical path length minus the longest path through the task. For example, if the critical path is 15 days and the longest path through task X is 11 days, the float of task X is 15 - 11 = 4 days. Tasks on the critical path have zero float.
What is the difference between an activity-on-node and an activity-on-arrow PERT chart?
In an activity-on-node chart the tasks sit at the nodes, in boxes containing the timings. In an activity-on-arrow chart the milestones sit at the nodes, in circles, and the tasks sit on the arrows. Activity-on-node is less cluttered and easier to read and amend.
What is float, and what is a milestone?
Float is the amount of time a task can be delayed before it affects the start of the next task. A milestone is a point in the project when tasks or criteria are met. A milestone is not a goal.
What are the advantages and disadvantages of a Gantt chart?
A Gantt chart gives a visual overview of the schedule and shows changes to the schedule clearly. Its drawbacks are that it needs skill to create, is time-consuming to update, cannot show every detail of a complex project and cannot allow for contingency time.
What do students get wrong when they describe float?
Describing how float is calculated does not answer the question. Float is the amount of time that a task can overrun before affecting the succeeding tasks, and this is the point examiners look for. Confusing a milestone with a goal is also a common error.